City gets updates on all Mississauga transit developments

City staff recently presented Mississauga council with an update on all rapid transit projects underway in the city. These include the Hazel McCallion Line, the Dundas East Bus Rapid Transit, the Lakeshore Bus Rapid Transit, the Downtown Transit Mobility Hub and the Eglinton Crosstown West Extension. Both the Hazel McCallion Line and the Eglinton Crosstown West are owned and led by Metrolinx. 

Metrolinx CEO Michael Lindsay also provided an update to council on April 22 on the progress of its projects but the update was held in a closed session that the public was not allowed to access. The McCallion Line’s slow progress, ongoing construction and traffic delays to date have been a regular source of frustration for Mississauga residents and business owners. 

City staff, however, say they are working closely with Metrolinx and its contractor, Mobilinx, to advance the construction of the McCallion Line wherever and whenever they can. Carolyn Ryall, Director of the Rapid Transit Program Office for Mississauga told council that residents should now see “an increased presence of crews” working on the line as the city has already issued 65 permits and licenses so far this year, which is an increase over last year and evidence that the pace of work is picking up. 

She also said the city is “actively applying lessons learned” from other Metrolinx projects, such as Toronto’s recently opened Finch West LRT. When Finch West opened in February this year it was widely criticized for being too slow. Toronto is now installing enhanced signals at intersections along the route, something that Ryall says Mississauga is also looking into for the Hazel McCallion Line.

HAZEL MCCALLION LINE

  • 18km from Port Credit GO Station to the Brampton Gateway Terminal
  • 19 stops
  • $4.6 Billion budget
  • Original Construction timeline: 2020-2024
  • Estimated completion date: 2028 or 2029

DUNDAS BRT

  • 7Km along Dundas St. E from Etobicoke Creek to Confederation Parkway
  • 8 stops
  • $405.7 Million budget
  • Construction timeline: late 2026/early 2027-2032

LAKESHORE BRT

  • 2km on Lakeshore between Etobicoke Creek and East Avenue
  • New boulevard space with cycle tracks, sidewalk and landscape zone
  • $89 Million budget
  • Construction timeline: 2027-2032

DOWNTOWN MOBILITY HUB AND TRANSITWAY CONNECTION 

  • Central terminal Integrating MiWay busses, GO transit, Hazel McCallion Line 
  • Will be second busiest GO bus terminal outside Union Station
  • Pre-planning and stakeholder engagement phase: January 2026-late 2027

EGLINTON CROSSTOWN WEST EXTENSION

  • 9.2Km from Mount Dennis Station to Renforth Drive
  • 6.4Km to be underground
  • 7 Stations
  • $4.7 Billion budget
  • Construction underway, possible completion date: 2030-3031
  • Plans for future extension to Pearson Airport

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Popular

More like this

Understanding and addressing diabetes across Canada

Roughly 12 million Canadians live with diabetes or prediabetes,...

FUREY: Peel schools presentation targets young men

Parents can make this an election issue, and tell their trustee candidates

Local officers honoured by MADD Canada

Scarborough police have removed many impaired drivers from the road over the past year

Majority of city’s fatal motorcycle crashes happened in Scarborough

Stats come as redesign of Kingston Road is in the works